Silver Valley bridges and overpasses to receive repairs beginning Monday, April 15



I-90 ramp at Pinehurst.

Work to repair six structures on Interstate 90 from Bennett Bay to Kellogg will start Monday, April 15.

Bridge decks on interstate ramps at Pine Creek in Pinehurst will be repaired first. A month-long detour to the Kingston exit is planned to be in place while crews work on the eastbound off-ramp.

Crews will move between bridges as they complete repairs, with the ramps at Pinehurst followed by the Airport Road overpass in Smelterville and the Bunker Avenue overpass in Kellogg. Bridges at Bennett Bay and the Kingston overpass are scheduled for improvements in May and June.

Work will pause for six weeks around July to allow water levels to lower so crews can apply protective paint to one structure in Pinehurst in August.

Bridges on the interstate may be reduced to one lane in each direction, and closures for structures over the interstate will vary with the location and availability of detours nearby. Drivers are advised to check 511.idaho.gov for the latest traffic impacts and to visit the website for more information.